Grid Operator PJM Denies Pause on Project Approvals

February 4, 2022 by Reece Nations
Grid Operator PJM Denies Pause on Project Approvals
Utility lines. (Photo by Dan McCue)

VALLEY FORGE, Pa. — PJM Interconnection, one of the nation’s largest regional transmission organizations, is denying reports that it is proposing a two-year pause on reviewing energy project applications.

PJM coordinates the transmission of wholesale electricity in portions or the entirety of 13 states and Washington, D.C., and has been grappling with a backlog in its interconnection request queue. The backlog and strategies to mitigate it was outlined in the organization’s January interconnection process reform update.

Inside Climate News reported on Wednesday PJM was proposing a two-year pause on reviewing energy projects which Chief Communications Officer Susan Buehler denied in a statement shared with The Well News. Another report published by pv magazine on Thursday parroted the claim that PJM was proposing a postponement of reviewing interconnection requests. 

Buehler said PJM is months away from instituting any changes to its interconnection process and that delays are not part of its plans going forward. Buehler also characterized media reports of the proposal as “horribly inaccurate.”

“PJM and stakeholders worked intensively for more than six months to reach a consensus on reforms that will speed the interconnection process for development projects and enhance cost transparency, among other improvements,” PJM said in a statement shared with The Well News. “These changes are critical for PJM to help states achieve their decarbonization goals, enable the grid of the future, and establish a more efficient process to handle the unprecedented influx of generation interconnection requests.”

The organization’s interconnection process reform update detailed its creation of an “Interconnection Process Reform Task Force,” which addresses procedural issues, identifies opportunities to reduce interconnection queue backlogs and proposes solutions. PJM is regulated by the Federal Energy Regulatory Commission, which must approve any planned changes to the grid operator’s interconnection process before they are instituted.

Project queue backlogs have become increasingly common as transmission organizations contend with an unprecedented number of generation requests. Last May, the Lawrence Berkeley National Laboratory conducted a study of all seven independent system operators and regional transmission organizations along with 35 additional utilities which found just 24% of connection projects nationwide from 2000 to 2015 were ultimately constructed.

Some of the proposal’s objectives are to accelerate the addition of renewable energy to the grid, prioritize projects ready for construction and streamline the interconnection process’s efficiency, Buehler said. Of the 225 gigawatts of generation projects already in PJM’s planning queue, 95%, or around 214 gigawatts, are renewable energy projects.

PJM’s plans for reforming their project approval process includes a multi-phase cycle of reviewing applications, conducting system impact analyses while determining planning level interconnection costs, undertaking studies and upgrades of applicant facilities, then negotiating final agreements with the applicants. The new process would allow for a multifaceted review of the applicants and their facilities while staggering subsequent cycles of new submissions and progression towards grid interconnection.

“This is a proposal [that] still has multiple steps to go through in the stakeholder process,” PJM said. “It goes before the Planning Committee on Feb. 8, and if approved, goes before the larger Markets and Reliability Committee and then Members Committee in April. If approved by members, PJM would need to file these recommendations with FERC in May.” 

Reece can be reached at [email protected].

A+
a-
  • energy energy projects
  • PJM Interconnection
  • transmission lines
  • In The News

    Health

    Voting

    Energy

    May 1, 2024
    by Dan McCue
    White House Finalizes New Environmental Permitting Rules

    WASHINGTON — President Joe Biden on Tuesday unveiled a new rule intended to speed up permitting for new clean energy... Read More

    WASHINGTON — President Joe Biden on Tuesday unveiled a new rule intended to speed up permitting for new clean energy projects by forcing agencies to adhere to strict deadlines — and page limits — when conducting their environmental reviews. The rule also streamlines the permitting process... Read More

    April 29, 2024
    by Dan McCue
    Philly Set to Celebrate Completion of Solar Farm Powering Municipal Buildings

    PHILADELPHIA, Pa. — Philadelphia Mayor Cherelle Parker, city officials and members of the municipal energy authority are set to gather... Read More

    PHILADELPHIA, Pa. — Philadelphia Mayor Cherelle Parker, city officials and members of the municipal energy authority are set to gather at City Hall on Tuesday to celebrate the long-awaited completion of the Adams Solar Project. The 70 MW facility not far from Gettysburg has been in... Read More

    April 29, 2024
    by Dan McCue
    NYS Eyes Three ‘Underutilized’ Sites for Renewable Energy Development

    ALBANY, N.Y. — The New York State Energy Research and Development Authority has signed three agreements to explore the possibility... Read More

    ALBANY, N.Y. — The New York State Energy Research and Development Authority has signed three agreements to explore the possibility for renewable energy development in the Southern Tier, Western New York and Long Island.  Under the terms of memorandums of understanding, the agency’s Build-Ready Program will... Read More

    April 29, 2024
    by Dan McCue
    Energy Department Seeks to Address Grid Interconnection Challenges

    WASHINGTON — It’s one thing to say you want to deploy more renewable and green energy. It’s another to solve... Read More

    WASHINGTON — It’s one thing to say you want to deploy more renewable and green energy. It’s another to solve transmission capacity issues, reduce charges on existing lines, and deploy new digital technology to strengthen grid resilience and reduce costs. In a bid to help, the... Read More

    April 29, 2024
    by Dan McCue
    New Nuclear Facility Opens Near Waynesboro, Georgia

    WAYNESBORO, Ga. — Plant Vogtle Unit 4, a nuclear power project that backers describe as one of the “largest clean... Read More

    WAYNESBORO, Ga. — Plant Vogtle Unit 4, a nuclear power project that backers describe as one of the “largest clean energy projects in the nation” has begun commercial operation near Waynesboro, Georgia, a bucolic town about 30 miles south of Augusta. The unit’s entry into commercial... Read More

    Tractor-Trailers With No One Aboard? The Future Is Near for Self-Driving Trucks on US Roads

    PITTSBURGH (AP) — On a three-lane test track along the Monongahela River, an 18-wheel tractor-trailer rounded a curve. No one... Read More

    PITTSBURGH (AP) — On a three-lane test track along the Monongahela River, an 18-wheel tractor-trailer rounded a curve. No one was on board. A quarter-mile ahead, the truck's sensors spotted a trash can blocking one lane and a tire in another. In less than a second,... Read More

    News From The Well
    scroll top